purchasing One Main Plaza, American Century Services needed
to install the necessary facilities to support moving staff.
BGR Engineers designed a hardening package which included a
redundant 24 hour cooling system, emergency generator and UPS
system, and computer room. The entire design utilizes a "2N"
platform. In addition, BGR Engineers provided a written commissioning
plan to test all redundant systems. |
|
|
|
 |